Yellowhead Trail Construction

Part of Yellowhead Trail Freeway Conversion

Road Construction New along Yellowhead Trail, drawn from 2 City of Edmonton construction permits active between 2023 and 2026.

Active

Corridor

Yellowhead Trail

Duration

2,860 days (~7.8 yrs)
Since project start

Status

Active

Work type

Road Construction New

Construction permits

2
Major permits; open since Jun 7, 2023

Daily traffic (AADT)

60,300
Measured on this corridor

Scheduled end

Oct 31, 2026

Permit types

The kinds of City construction permits aggregated for this corridor.

  • Bridge Rehabilitation1 permit
  • Road Construction New1 permit

Impact metrics

Estimated

Estimated vehicles affected

172.5M

daily traffic volume (AADT) × construction days

Estimated cumulative delay

5.7M hrs

Flagged impacts

PedestrianOn-street parking

Methodology & sources

Vehicle and delay figures are transparent estimates. Every other field (corridor, status, dates, duration, impact flags) is drawn directly from open data.

Start dates default to the earliest currently-open City permit. OSCAM drops permits once they close, so a project’s earlier phases are not in open data. Corridors marked “official” use a hand-verified inception date from City of Edmonton project pages.

Data as of Jul 8, 2026. Sources: