← Back to overview

Project detail

St Albert Trail Construction

Road Construction New along St Albert Trail, drawn from 2 City of Edmonton construction permits active between 2023 and 2026.

Active

Corridor

St Albert Trail

Earliest open permit

Jun 7, 2023
Open-permit start — earlier phases aren’t retained in open data.

Duration

1,242 days (~3.4 yrs)
Current permit window

Status

Active

Work type

Road Construction New

Construction permits

2
Major road-construction permits (excludes maintenance)

Daily traffic (AADT)

36,100
Measured on this corridor

Scheduled end

Oct 31, 2026

Impact metrics

Estimated

Estimated vehicles affected

44.8M

daily traffic volume (AADT) × construction days

Estimated cumulative delay

1.3M hrs

Flagged impacts

PedestrianBike facilitiesOn-street parking

Methodology & sources

Vehicle and delay figures are transparent estimates. Every other field (corridor, status, dates, duration, impact flags) is drawn directly from open data.

Start dates default to the earliest currently-open City permit. OSCAM drops permits once they close, so a project’s earlier phases are not in open data. Corridors marked “official” use a hand-verified inception date from City of Edmonton project pages.

Data as of Jul 8, 2026. Sources: