Victoria Trail Construction

Road Construction Rehab along Victoria Trail, drawn from 2 City of Edmonton construction permits active between 2026 and 2028.

Active

Corridor

Victoria Trail

Earliest open permit

Jul 2, 2026
Open-permit start. Earlier phases aren’t retained in open data.

Duration

882 days (~2.4 yrs)
Current permit window

Status

Active

Work type

Road Construction Rehab

Construction permits

2
Major road-construction permits (excludes maintenance)

Daily traffic (AADT)

16,900
Measured on this corridor

Scheduled end

Nov 30, 2028

Impact metrics

Estimated

Estimated vehicles affected

14.9M

daily traffic volume (AADT) × construction days

Estimated cumulative delay

496.9K hrs

≈2.0 min/vehicle, from this corridor’s permit restrictions

Flagged impacts

PedestrianBike facilities

Methodology & sources

Vehicle and delay figures are transparent estimates. Every other field (corridor, status, dates, duration, impact flags) is drawn directly from open data.

Start dates default to the earliest currently-open City permit. OSCAM drops permits once they close, so a project’s earlier phases are not in open data. Corridors marked “official” use a hand-verified inception date from City of Edmonton project pages.

Data last updated . Sources:

Permit types

The kinds of City construction permits aggregated for this corridor.

  • Bridge Rehabilitation1 permit
  • Road Construction Rehab1 permit