91 Street Construction

Road Construction Rehab along 91 Street, drawn from 5 City of Edmonton construction permits active between 2025 and 2026.

Active

Corridor

91 Street

Earliest open permit

May 26, 2025
Open-permit start — earlier phases aren’t retained in open data.

Duration

523 days (~1.4 yrs)
Current permit window

Status

Active

Work type

Road Construction Rehab

Construction permits

5
Major road-construction permits (excludes maintenance)

Daily traffic (AADT)

24,850
Measured on this corridor

Scheduled end

Oct 31, 2026

Impact metrics

Estimated

Estimated vehicles affected

13M

daily traffic volume (AADT) × construction days

Estimated cumulative delay

173.3K hrs

0.8 min/vehicle, from this corridor’s permit restrictions

Flagged impacts

PedestrianBike facilitiesOn-street parking

Methodology & sources

Vehicle and delay figures are transparent estimates. Every other field (corridor, status, dates, duration, impact flags) is drawn directly from open data.

Start dates default to the earliest currently-open City permit. OSCAM drops permits once they close, so a project’s earlier phases are not in open data. Corridors marked “official” use a hand-verified inception date from City of Edmonton project pages.

Data as of Jul 8, 2026. Sources:

Permit types

The kinds of City construction permits aggregated for this corridor.

  • Road Construction Rehab5 permits